Saturday, 8 August 2015

CS615 Software project manager

Question # 1 of 10 ( Start time: 09:29:50 AM )
Total Marks: 1
The British Standards Institution (1986) has stated the quality as
Select correct option:

        
·      The ability of a software product to satisfy its specified requirements

·      "An inherent or distinguishing characteristic or a property"

·      “Quality is in the eye of the beholder, a matter, of the client's judgment.”

·      All of the given


Question # 2 of 10 ( Start time: 09:30:33 AM )       Total Marks: 1
The check-in and checkout facilities provide___________
Select correct option:

·   Best control
·   Best control
·   SCI control
·   Synchronization control


Question # 3 of 10 ( Start time: 09:30:59 AM )       Total Marks: 1
A baseline version __________
Select correct option:

·   Have a short life
·   Can be assigned version numbers 3.2
·   Tested and certified version of a system
·   Survive only during bug fixing                                    

Question # 4 of 10 ( Start time: 09:31:47 AM )       Total Marks: 1
You can use the Item Traceability Matrix to identify _______ at the end of each phase
Select correct option:

·   SCIs
·   SCM
·   Design
·   Construction


Question # 5 of 10 ( Start time: 09:32:18 AM )       Total Marks: 1
Defined scope is a
Select correct option:

·      Technology-related problems
·      Product-related problems
·      Process-related problems
·      People-related problems                                      

 
Question # 6 of 10 ( Start time: 09:33:13 AM )       Total Marks: 1
Software requirements engineering is a process of all except
Select correct option:

·      Discovery 
·      Refinement
·      Design
·      Specification


Question # 7 of 10 ( Start time: 09:33:56 AM )       Total Marks: 1
The model serves as the basis for the creation of ________ for the Software.
Select correct option:

·      Design
·      Maintenance
·      Testing
·      Specifications


Question # 8 of 10 ( Start time: 09:34:34 AM )       Total Marks: 1
Most software project manager’s practice a lot of management techniques that are of doubtful authenticity are called
Select correct option:

·      Project management tools
·      Project management myths
·      Project management thumb rules
·      Project management fundamentals



Question # 9 of 10 ( Start time: 09:35:20 AM )       Total Marks: 1
The Introduction of the software requirements specification states the
Select correct option:

·   Goals
·   Objective
·   Design
·   Goals and objectives of the software


Question # 10 of 10 ( Start time: 09:35:53 AM )     Total Marks: 1
The quality of software is said to be high if it meets the
Select correct option:

·   Standards, defined for the product
·   Procedures, defined for the product                     
·   Standards and procedures, defined for the product
·   Design defined for product




MC090409429 : Sharqa

Question # 2 of 10 ( Start time: 06:01:17 PM )         Total Marks: 1
The distinguishing characteristics of a software product are _________
Select correct option:

  
  
  
  


Question # 3 of 10 ( Start time: 06:02:15 PM ) Total Marks: 1
Insufficient identification is a
Select correct option:

  
  
  
  

Question # 4 of 10 ( Start time: 06:03:38 PM ) Total Marks: 1
________of the system is an effort to better understand data and control flow, functional processing, operational behavior, and information content
Select correct option:

  
  
  
  


Question # 5 of 10 ( Start time: 06:04:56 PM ) Total Marks: 1
These all are Product Transition Factors except
Select correct option:

  
  
  
  

Question # 6 of 10 ( Start time: 06:06:07 PM ) Total Marks: 1
Inefficient project management style is a
Select correct option:

  
  
  
  


Question # 7 of 10 ( Start time: 06:07:18 PM ) Total Marks: 1
Finally, the specification includes a ________
Select correct option:

  
  
  
  


Question # 8 of 10 ( Start time: 06:07:39 PM ) Total Marks: 1
Software design is actually a multi step process that focuses on distinct attributes of a program, these are
Select correct option:

  
  
  
  

Question # 9 of 10 ( Start time: 06:08:23 PM ) Total Marks: 1
Software requirements analysis may be divided into______ areas of effort
Select correct option:

  
  
  
  


Question # 10 of 10 ( Start time: 06:09:16 PM ) Total Marks: 1
McCall (MCC77) and his colleagues proposed some software quality factors based on _________ most important aspects of a software product:
Select correct option:

  
  
  
  


CS615 – Software Project Management
Online Quiz # 2

Total Questions: 8


Question # 1 of 8 ( Start time: 07:32:00 PM )  Total Marks: 1 
…………. theory when the deliverables of a project are more important than its phases. This normally happens when the deliverables are decided before the project begins. 
Select correct option: 

 Project life-cycle-based
 Scheduled

 None of given
 Deliverable-based (handouts pdf file, page 277)



Question # 2 of 8 ( Start time: 07:32:54 PM )  Total Marks: 1 
Predecessor activities need to ------------ before the next can begin. After a predecessor activity is completed, the successor activity becomes the predecessor for another activity. 
Select correct option: 

 Both start and end

 End (handouts, page 297)


 Start
 None of given 


Question # 3 of 8 ( Start time: 07:33:30 PM )  Total Marks: 1 

MCQ,S



Each …………. can be subdivided into sub tasks. 
Select correct option: 

 None of given
 Program

 Task (handouts, page 275)


 Project
Question # 4 of 8 ( Start time: 07:34:01 PM )  Total Marks: 1 
Using PERT and CPM, -----------------------, helps you complete a project on time. By using these techniques, you can determine the latest time by when an activity should start to be completed on time. 
Select correct option: 

 Individually 


 Combination

 Individual and Combine (handouts, page 296)

 None of given  

Wednesday, 5 August 2015

CS201 4th ASSIGNMENT.

CS201 4th ASSIGNMENT.

#include <iostream>
#include <stdlib.h>
using namespace std;
class StaffRegistration
{
private:
char cnic[18];
char name[30];
char fname[50];
char dob[11];
char degree[10];
char desig[15];
char sal[10];
char joinDate[11];
char cell[13];
char address[40];
public:
void InputStaffData()
{
                //enter your full name//

cout<<"Program developed By: "<<endl;
                //enter your vu id
cout<<"My VU ID : "<<endl;

cout<<"\nPlease enter National Identity Card Number(CNIC)"<<endl;
cin.getline(cnic,18);
cout<<"Please enter name"<<endl;
cin.getline(name,30);
cout<<"Please enter father name"<<endl;
cin.getline(fname,50);
cout<<"Please enter date of birth (dd/mm/yyyy)"<<endl;
cin.getline(dob,11);
cout<<"Please enter qualification"<<endl;
cin.getline(degree,10);
cout << "Please enter designation:" << endl;
cin.getline(desig,15);
cout<<"Please enter salary"<<endl;
cin.getline(sal,10);
cout<<"Please enter joining date (dd/mm/yyyy)"<<endl;
cin.getline(joinDate,11);
cout<<"Please enter contact number"<<endl;
cin.getline(cell,13);
cout<<"Please enter address information"<<endl;
cin.getline(address,40);
cout<<"\nRecord added successfully !!!"<<endl;
}
void DisplayStaffData()
{
cout<<"CNIC: \t\t\t"<<cnic<<endl;
cout<<"Name: \t\t\t"<<name<<endl;
cout<<"Father Name: \t\t"<<fname<<endl;
cout<<"DoB: \t\t\t"<<dob<< endl;
cout<<"Qualification: \t\t"<<degree<<endl;
cout<<"Designation: \t\t"<<desig<<endl;
cout<<"Salary: \t\t"<<sal<<endl;
cout<<"Joining Date: \t\t"<<joinDate<<endl;
cout<<"Contact Number: \t"<<cell<<endl;
cout<<"Address: \t\t"<<address<<endl;
}
};
main()
{
system("cls");
StaffRegistration emp;
emp.InputStaffData();
cout<<"---------------------------------------------------------------------------"<<endl;
cout<<"\t \t \t DISPALAY STAFF INFORMATION"<<endl;
cout<<"---------------------------------------------------------------------------"<<endl;
emp.DisplayStaffData();
cout<<"---------------------------------------------------------------------------"<<endl;
system("pause");

}

CS201 INTRODUCTION TO PROGRAMMING COMPLETE SOLVED PAPER

CS201- Introduction to Programming Complete Solved Paper

MIDTERM  EXAMINATION
Spring 2009

CS201- Introduction to Programming (Session - 1)
Question No: 1      ( Marks: 1 ) - Please choose one

In C/C++ the #include is called,
Header file

Preprocessor Directive
Statement

Function
Question No: 2      ( Marks: 1 ) - Please choose one

To access the element of two dimensional array we use,
Single referencing

Single dereferencing
Double dereferencing

Double referencing
Question No: 3      ( Marks: 1 ) - Please choose one

Data Size of the file is always _________ the actual size of the file.
Greater than

Equal to
Less than or equal to

None of the above
Question No: 4      ( Marks: 1 ) - Please choose one

When an identifier is declared with keyword const then,
Its value can be changed during execution.

Its value can not be changed
Its value can be changed with arithmetic operator

Its value can be overwritten
Question No: 5      ( Marks: 1 ) - Please choose one

In C/C++ if we define an array of size eight (8) i.e. int Arr [8]; then the last
element of this array will be stored at,

Arr[0]
Arr[8]

Arr[7]
Arr[-1]

Question No: 6      ( Marks: 1 ) - Please choose one
If it is required to copy an array to another array then,

Both arrays must be of the same size and data type
Both arrays may be of different size

Both arrays may be of different data type
Both arrays may be of different size and type

Question No: 7      ( Marks: 1 ) - Please choose one
In C/C++ all character strings are terminated with,

Null character
String

Zero
Full stop

Question No: 8      ( Marks: 1 ) - Please choose one
Let suppose

struct intorDouble{
Int ival;

Double charvar;
};

main(){
intorDouble  VAZ;

int size ;
size = sizeof(VAZ);

}
What will be the value of variable size, if int occupies 4 bytes and double occupies 8

bytes?
2

4
8

12
Question No: 9      ( Marks: 1 ) - Please choose one

When a pointer is incremented, it actually jumps the number of memory
addresses

According to data type
1 byte exactly

1 bit exactly
A pointer variable can not be incremented

Question No: 10      ( Marks: 1 ) - Please choose one
Do-while loop executes at least,

Zero Time
One Time

Two Times
N Times

Question No: 11      ( Marks: 1 ) - Please choose one
+= ,  *= ,  /= ,  etc are called,

Assignment operators
Logical operator

Compound assignment operator
Unary operator

Question No: 12      ( Marks: 1 ) - Please choose one
Computer can understand only machine language code.

True
False

Question No: 13      ( Marks: 1 ) - Please choose one
Which of the following is the correct syntax to print multiple values or variables in

a single command using cout?
cout << "Hello" + x + "\n";

cout << "H" << x << "\n";
cout << "H", x, "\n";

cout << ("H" & x & "\n");
Question No: 14      ( Marks: 1 ) - Please choose one

The compilers and interpreters also belong to the System Software category.
True

False
Question No: 15      ( Marks: 1 ) - Please choose one

Editors are used to compile the code.
True

False
Question No: 16      ( Marks: 1 ) - Please choose one

The variables having a name, type and size are just like empty boxes.
True

False
Question No: 17      ( Marks: 1 )

For Exclusive Projects, Reports & Latest Papers
What will be the result of the statement?

rand ( ) % 50
Question No: 18      ( Marks: 1 )

What is the ASCII code of null character and how is it represented?



                       CS201 INTRODUCTION TO PROGRAMMING COMPLETE SOLVED PAPER....


Question No: 19      ( Marks: 2 )

What is a truth Table?
Question No: 20      ( Marks: 3 )

How learning to design programs is like learning to play soccer?
Question No: 21      ( Marks: 5 )

What is the purpose of the default statement in the switch statement?
Question No: 22      ( Marks: 10 )

Write a program which contains a user defined function named
ConvertInSeconds

that
takes 3 integer arguments hours, minutes and seconds, this function converts the time into

seconds and returns the number of seconds.
Input variables hours , minutes and seconds in main program and call the function

ConvertInSeconds
and display the number of seconds returned by function.

Hint:
1 hour =60 minutes
1 minute =60 seconds